Every project starts with what you need. You can order design only, add periodic supervision, or choose close supervision throughout the works. Even without supervision, clients can call us with any question.

  1. Design

    Electrical systems designed for the project: switchboards, power, lighting and control circuits, air-conditioning feeds, lighting control, and motor and fan control.

    What you receive: Design, a switchboard sketch and a bill of quantities, for the board alone or the whole project, including estimates. On large projects and on request, also a works specification.

  2. Periodic supervision

    Site visits at an agreed frequency, for example every two weeks, monthly or every two months.

    What you receive: A visit report.

  3. Close supervision

    Close follow-up of the works, up to daily or full on-site supervision, as the project requires.

    What you receive: A visit report, and checks against what the specification says.

What happens without design and supervision

Common questions

What is the difference between periodic and close supervision?

With periodic supervision we visit the site at agreed times, for example every two weeks or once a month. Close supervision means a closer presence, up to daily or full on-site supervision.

Can I order design only?

Yes. You can order design alone and add supervision as needed.

What do I receive after a site visit?

A visit report.

What is the work checked against?

The design and the project specification. On large projects and on request, the client also receives a works specification.

What does the bill of quantities include?

As needed: the switchboard alone or the whole project, including estimates, working hours, infrastructure and points.

Can I call when there is no supervision?

Yes. Clients can call us with any question.

Example: what supervision checks

On large projects and on request, the client receives a works specification, and supervision checks what is written in it. These hold points come from a specification for extending a dining hall in an operating hotel. At each stage, work does not continue until it has been checked. Supervision follows the stages of the works.

Hold points before work continues

StageWhat is checkedCondition to continue
Before dismantlingMapping of sources and loads, disconnection and relocation planApproval by the supervisor and maintenance, and verified safe isolation
Before switchboard manufactureComplete switchboard file and design dataDocumented technical approval by the designer
Before pouring foundationsFoundation earthing and its connections, where requiredInspection and records before covering
Before closing walls or floorsConduit, boxes, routes and quantitiesSupervisor inspection and completed records
Before closing the ceilingSupports, separation, access, connections and locationsApproval of concealed work and closed defects
Before hiding fire stoppingApproved detail, system type, workmanship and labelsApproval by the party defined for the project
Before switchboard deliveryFactory test report, match to the file, labellingRelease according to the control plan
Before energizingPreliminary tests, continuity, insulation and settingsEnergizing procedure approved by the authorized parties
Before an alternative source testTest procedure, loads and effect on the facilityApproval by maintenance and the supervisor
Before opening the areaTest approvals, emergency lighting and handoverHandover approval for the defined section
The cover page of a real specification, in Hebrew.
The cover page of a real specification, in Hebrew.
The hold points page from the same specification, in Hebrew.
The hold points page from the same specification, in Hebrew.

Sample clauses

What is handed over at the end

Sample visit report

After each visit the client receives an organized report, by execution stage.

Sample format, in Hebrew. The data is not from a real project.
Sample format, in Hebrew. The data is not from a real project.
  • By execution stageThe report shows which stage the project is at, and what was checked at that stage.
  • Defects and follow-upEach defect has a location, a responsible party, a target date and a status, until it is closed.
  • PhotosA record of what was found and of the repair.
  • Decision and next stepsWhether work can continue, and what will be checked at the next visit.